For the needs of the Investor of JKP “Novosadska toplana”, works were performed on the complete reconstruction of the management and supervision system at the facility “GRS” (Main Distribution Station). The following works were performed:

  • Dismantling of old electric and electric 0.4kV distribution cabinets;
  • Disassembly of control cabinets and control systems;
  • Production, installation and connection of new distribution cabinets for power supply of all 0.4 kV electric power and electric motor consumers in GRS;
  • Development of new control and supervision distribution cabinets;
  • Software development for Touch Panel and Scada application;
  • Creating connection schemes;
  • Testing and commissioning of the plant locally and remotely.